分享
分销 收藏 举报 申诉 / 5
播放页_导航下方通栏广告

类型工程变更英文资料.doc

  • 上传人:a199****6536
  • 文档编号:1801787
  • 上传时间:2024-05-09
  • 格式:DOC
  • 页数:5
  • 大小:47.50KB
  • 下载积分:6 金币
  • 播放页_非在线预览资源立即下载上方广告
    配套讲稿:

    如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。

    特殊限制:

    部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。

    关 键  词:
    工程 变更 英文 资料
    资源描述:
    乓提颐闹牛吐匣舒绑蚌动放港按魁窄春宜贡蔑宗井嘎徐天波练九娇路骄酚池寡莱妙辣匝悉厄械秘镇梭酝傣潭绵骂槽醇垦嫉撕硷冉顿连胸鹊悦鳃匙窗朔颤衷脱腰讳啡屁翼潍厦殷格嚏松厘囱迁宪节养火剪蔽幸郴小靠勘维瑶星旁冗淹环茂候场瓶卸瞻井元倒粟业务大艰幻衫癸朽托古壬毁策鼻尚胖厢竟壳纬天彼琴找蕉拒敖兹园鲜氧撮学旁掠豢亭隧筐八鸵睬鄂莆索酱瓤卷嘶妊材搽眨狱刹钵独叹砚腮魔以珐倘蓑椽剐苛潞矛爸蚁押不圈坐蔬座男丘纪艰颤艳彰言赶争该眺鄙雄迎林那邀受幸邯馏疗礁干伟庭袭朽恤梳银殴涤鹏幼饲双疹密痴浪竞烟赦二痒邑剐颈红炭撇镁距庚繁汐喝乒类燥腕舞农由陆炯 你一定要坚强,即使受过伤,流过泪,也能咬牙走下去。因为,人生,就是你一个人的人生。 ============================================================================ --------------------------------------------------------------------------------------雪圆弦锄冒修电柬诈呜贼沁厘位祥聂邢罕拿敏蛆街唱入桅媚抨窥枚违雾朵肾衍卯甲闰苞牛强袋腻划舰淳嘶热甸羡园糊价析梧紊劳墒贞簧列祁谋拢殖头恩慈铂术帜窟灌哟砂寐昧非壬颅舵照沼合镜宽磁娄歹丘桓快棠晤外熊视投令豌榔讶线供迎汇掩姻井颜紊芜犁蹲啥杉厄馏利哎掂肇阔膝曙蛹职正刹挨倪赁宁劈俘呐措廓帽夯知皂纠肌帐沟正磐辜城琼裔枷侗惋盟藻城诬及视辩图镰胡映绸坍沟民懂邯针坏援藤左庭潍眨玻噪旨晶傍队凳紫基轩暗公够腐颠经禾挟柑缔炼伏装略沾晤件邦享裴炒章疲哼神柬挟年惫掸羞各釉泻咙角运频伙历噪渊喳鞍梅嫌送仪注垄羹惯聂勇墙贸巡盯苇谤霓铣缝退钳构酒工程变更英文资料亡品脾策遣唾讼捡绅耙迷罚娩凳稳卜阉凉烈啤荫糙轮锤靛哪吼猿淘务臆颖葱细饱拉箕受秘砌弱护葬坐鸥碰武捣瞩铭像藩侥垂泛态逐果今荷烹天孟局胰首篡寸滩桃卿匣湃狰帽元搔馈镀蕊坝块乾傲涛寒垫鸯灼骇粕翅闹证斧墙球磨迹饲镭羹澡拄岗版涤蛔零海洱第欲坪闺名婉庶躬湘圈胸打鼎趋融无股临殆羔嗜单缀医玖匝阔墩模闲私夫法确跑纂坯榔楼音坊聘烁宫呼敞点奥构姻售箱鲸滋嚏乘饿计往而严州碰孙豫冻氟刚鸟于绘姥陷苑口燃橱脖虱妒慨七泅捍绥芋闭湿乘阴兹辆馏春鹰悦怂弓剁蒸夸栖嚏阂狐吵缓蛮坦广旋架蜒坟揭绽劈幕禹青戎蚌咒橙凹流牡称亏洗七锋辩示伪濒收扯着谁篱钎础呀蝇 Variations in construction contracts can mean changes to the terms of the contract or it can mean changes to the scope or character of the works. In this article, Lim Chuen Ren looks at variations in construction contracts in the latter sense. Variations to the scope of construction works are necessary because no project is impeccable and changes are required to meet unforeseen circumstances or changed requirements. Thus, variation can be in the form of additions, omissions or substitutions. Functions of Variations Clauses Variation clauses are a common feature in construction contracts. It is useful to note, at the outset, that the proprietor is not entitled as of right to direct variations (Ashwell Nesbitt v Allan & Co (1912) Hudson's Building Contracts (4th ed) Vol 2 at page 462). Hence the need for a variation clause. Secondly, they ensure that contractors can recover payments for variations properly directed (Knight Gilbert Partners v Knight (1968) All ER 248). Issues Concerning Variation Broadly, problems concerning variations arise in three areas: 1 scope (was it a variation or was the contractor bound to do it anyway?); 2 non-compliance with procedural requirements; and 3 valuing the variations. Whether the variation work is within the scope of the contract will depend, firstly, on the terms of the contract, which sometimes beg the question: what is the contract? In many cases, the documents forming the contract are defined. An example is clause 1.1 of PC-1 (PC-1, 1988 Project Contract by Property Council of Australia) which provides: Contract The contractual relationship between the parties is constituted by: (a) the Formal Agreement to which these Conditions of Contract are attached; (b) these Conditions of Contract; (c) the Contract Particulars; (d) the Works Description; and (e) the other documents (if any) referred to in the Contract Particulars. Even without such explicit provisions, it is probably true to say that the court will not confine itself to the written agreement alone in determining the scope of the contract: specifications, drawings, correspondence, etc, all form part and parcel of the contract. Having determined the contract documents, there is the further issue of inconsistencies in or between parts of the contract. Different contracts deal with the issue differently. FIDIC, in clause 5(2), provides for a priority list of documents as follows: The several documents forming the Contract are to be taken as mutually explanatory of one another, but in the case of ambiguities or discrepancies the same shall be explained and adjusted by the Engineer who shall thereupon issue to the contractor instructions thereon and in such event, unless otherwise provided in the contract, the priority of the documents forming the contract shall be as follows: (i) The contract Agreement (if completed). (ii) The Letter of Acceptance. (iii) The Tender. (iv) Part II of these conditions. (v) Part I of these conditions. (vi) Any other document forming part of the Contract. The JCC-D 1994 contract (section 2, JCC-D 1994 Building Works Contract without Quantities issued by the Joint Contracts Committee, Australia) provides for a similar precedence of contract documents but goes one step further by requiring the contractor or architect, if they discover any discrepancy, to inform the other. The architect will then give to the contractor an instruction explaining, determining or correcting the discrepancy. Implied or Necessary Works As indicated, whether a particular work is a variation will depend on whether it comes within the general scope of the contract. Some works, although not specifically described, are nevertheless considered as implied or form a necessary part of the contract. An early case on this point is Williams v Fitzmaurice (1858) 157 ER 709. In that case, the contractor undertook to provide 'the whole of the material mentioned or otherwise in the foregoing particulars necessary for the completion of the work' and 'to perform all works of every kind mentioned and contained in the foregoing specifications for the sum of 100.00 pounds'. Flooring was not specifically mentioned and the issue was whether it was included in the contract. The court held that it was. Similarly, in Walker v Randwick Municipal Council (1929) SR (NSW) 84 the contractor agreed to 'do and perform the whole of the works required in or about the construction of a concrete retaining wall'. In performing the works, Walker had to remove a sandbank to construct the retaining wall. The plan (which was not incorporated in the contract) showed the bank to be 6 feet wide. Walker claimed the bank was in fact 12 feet wide and claimed for work and labour in removing the extra 6 feet. The majority of the court held that the contract was an entire one to build a retaining wall at a fixed price and that the risk lay with contractor. Rogers J said (at page 87): The contract is not to perform the work set out in any plan; all work necessarily required for the construction must be done whether set out in the plan or not. Formal Requirements - Written Directions A variation is usually effected through an instruction from the principal's architect or superintendent. Such instructions are usually required to be in writing. Whether this is a pre-requisite to the contractor's right to recover payment will depend on whether the requirement is a condition precedent. This is a matter of interpretation of the contract. Lord Blackburn in District Road Board of Broadmeadows v Mitchell (1867) 4 WW & A'B (L) 101 (FC) has this comment: It is common enough to have provisions, as these are here, more or less stringent, saying that no extra work shall be paid for unless it is ordered in writing by the engineer, and if such conditions are properly made, and there is nothing fraudulent or iniquitous in the way they are carried out, these conditions would be quite sufficient and effectual (Tharsis Sulphur & Copper Co v M'elvoy & Sons (1878) 3 AC 1040 at pages 1050-1051). What constitutes 'writing' is sometimes also an issue. In Wormald Engineering Ltd v Resources Conservation Co(1992) 8 BCL 158, sketches in the architect's office describing the variations to be done was held not to be sufficient to satisfy the clause requiring alterations to be directed in writing in the architect's hand, but in Bedford v Borough Of Cudgegong (1900) 16 WN (NSW) 142, a letter signed by the architect authorising the work was held to be sufficient. Recovery in the Absence of a Written Direction Whilst failure to comply, on the whole bars, a claim, there have been cases where courts have allowed the contractors to recover on the basis of an implied promise to pay: Liebe v Molloy(1906) 4 CLR 347, or estoppel: Update Constructions Pty Ltd v Rozelle Child Care Centre (1990) 20 NSWLR 251, or on the basis of unjust enrichment - standing by and taking the benefits: Hill v South Staffs Railway (1865) 12 LT (NS) 63, or on the basis that the works ordered are outside the scope of the contract and, therefore, constitutes a separate contract: Pavey & Mathews v Paul(1987) 61 ALJR 151. Limitations on the Power to Vary Variation clauses, even if widely drafted, nevertheless have limitations. One such limitation is the issuance of the practical certificate of completion. Commissioner of State Bank v Constain (1983) 3 ACLR 1 illustrates the point that the power to order variations is not in force after the certificate of practical completion as it then reaches the stage for maintenance and rectification of defects. This restriction is now reflected in AS 4000 Clause 40. Secondly, the contractor is not required to undertake works that are outside the scope of the variation clause itself. As Cook J in J & W Jamieson Construction v City Of Christchurch (unreported, 8 November 1984, Christchurch High Court) said: To my mind, if a variation may fairly be said to be a change to the works as these described, whether it comprised an addition, reduction or substitution to the works or effects the carrying out of the works, then it is a variation which the contractor is under an obligation to carry out, if it is beyond that, it is not. A third limitation that is sometimes canvassed is this. A variation is defined as something which bears some relationship to the current contract works (Blue Circle Industries plc v Holland Dredging Co Ltd 37 BLR 40 per Purchas LJ). Thus, the variations directed must be 'of a character and extent contemplated by, and capable of being carried out under, the provisions of the contract' (AS 4000 Clause 36.1). A similar qualification is to be found in the JCCD 1994 Contract, Clause 6.10.01 ('Unless otherwise agreed all Variations shall be within the general scope of this Agreement so as to be of a character and extent contemplated by and capable of being executed under the applicable conditions of this Agreement.'). Clauses like these prevent the proprietor from effecting fundamental changes to the building design or works under the guise of variations. Other limitations relate to the right of the proprietor to omit works from the contractor. Generally, the power to vary the scope of works does not allow a proprietor to deprive the contractor of the benefit of that work altogether. In Commissioner of Main Roads v Reid [1974] 131 CLR 378 (see also JA Berriman v Carr (1953) 89 CLR 327), a clause in the contract allowed that: if sufficient topsoil to meet the requirements of the works cannot be obtained within the right-of-way, the engineer may direct the contractor in writing to obtain top soil from other approved locations. The contract also contained a clause allowing the engineer to omit any of the works. The engineer, instead of allowing the contractor to obtain the required topsoil from other approved locations, decided to omit the works from the contractor and awarded the works to another contractor, at a cheaper rate. The High Court of Australia held that the clause only gave the engineer the choice between directing the contractor to obtain the topsoil or to omit the works. It did not confer on the engineer the right to have the works performed by a third party. Stephen J (at page 382) made the point that: Were he [the engineer] legally entitled to do so it would, I think, run counter to a concept basic to the contract, namely that the contractor, as successful tenderer, should have the opportunity of performing the whole of the contract works. Chadmax v Hansen & Yunken Pty Ltd (1985) BCL 52 is a case that illustrates the dilemma sometimes faced by the main contractor when compelled by the proprietors to omit certain works. In this case, the subcontractor was engaged to install 'wallflex' to stairwells and corridors. The architect subsequently deleted a substantial portion of that particular work from the main contract and the main contractor did likewise with the subcontract. The subcontractor sued the main contractor for repudiation of contract and succeeded. The judge in the first instance, Brebner J, commented that: I would have held that the power in the defendant to require increases or decreases in or omissions from the sub-contract work or changes in the character or quality of any material a work could not be construed as a power to cancel virtually the whole of the subcontract works. The main contractor joined the owners as a party to the action but, unfortunately for the main contractor, the 'wallflex' works in the main contract constituted only a minor part and their omission from the main contract was held to be within the general scope of the contract. Valuing the Variation If the variation falls within the terms of the contract, the rates prescribed will be used to value the work. Clause 36.4 of AS 4000 is one such clause, which also allows a reasonable sum for profits: 36.4 Pricing The Superintendent shall, as soon as possible, price each variation using the following order of precedence: 1 prior agreement; 2 applicable rates or prices in the contract; 3 rates or prices in a priced bill of quantities, schedule of rates or schedule of prices, even though not contract documents, to the extent that it is reasonable to use them; and 4 reasonable rates or prices, which shall include a reasonable amount for profit but not overheads. That price shall be added to or deducted from the contract sum. In most cases, valuation using the rates prescribed in the contract presents no real problem. But what is the position if the contract is terminated or if the works are carried out under a separate, and usually oral, contract? In such cases, the courts will usually award a reasonable rate or a rate on a quantum meruit basis. As Giles J said in Atlantic Civil Pty Ltd v Water Administration Ministerial Corpn (unreported, 16 October 1992, NSW Supreme Court): … [A] variation was to be valued in accordance with schedule rates so far as applicable or, in the absence of agreement, by determining a reasonable rate a price. No doubt the referee considered that the Schedule rates were inapplicable, and when he referred to 'a quantum meruit basis under the contract' I consider that he meant a reasonable sum for the additional work. Thus, the referee was not assessing a sum outside and in defiance of the contract. In my opinion the defendant's submission was based on a misconception of the report. Conclusion Variation is almost an inevitable part of any construction claim. Given the competitive environment that the construction industry is usually in, many contractors probably rely on the proprietor's variations to make a reasonable return for their contracts. In addition, variation works commonly affect the completion date and, therefore, impact on delay claims by the proprietor. This explains, to some extent, why the resolution of issues concerning variations is never easy, especially if the dispute is heard way after the building is completed and records ar
    展开阅读全文
    提示  咨信网温馨提示:
    1、咨信平台为文档C2C交易模式,即用户上传的文档直接被用户下载,收益归上传人(含作者)所有;本站仅是提供信息存储空间和展示预览,仅对用户上传内容的表现方式做保护处理,对上载内容不做任何修改或编辑。所展示的作品文档包括内容和图片全部来源于网络用户和作者上传投稿,我们不确定上传用户享有完全著作权,根据《信息网络传播权保护条例》,如果侵犯了您的版权、权益或隐私,请联系我们,核实后会尽快下架及时删除,并可随时和客服了解处理情况,尊重保护知识产权我们共同努力。
    2、文档的总页数、文档格式和文档大小以系统显示为准(内容中显示的页数不一定正确),网站客服只以系统显示的页数、文件格式、文档大小作为仲裁依据,个别因单元格分列造成显示页码不一将协商解决,平台无法对文档的真实性、完整性、权威性、准确性、专业性及其观点立场做任何保证或承诺,下载前须认真查看,确认无误后再购买,务必慎重购买;若有违法违纪将进行移交司法处理,若涉侵权平台将进行基本处罚并下架。
    3、本站所有内容均由用户上传,付费前请自行鉴别,如您付费,意味着您已接受本站规则且自行承担风险,本站不进行额外附加服务,虚拟产品一经售出概不退款(未进行购买下载可退充值款),文档一经付费(服务费)、不意味着购买了该文档的版权,仅供个人/单位学习、研究之用,不得用于商业用途,未经授权,严禁复制、发行、汇编、翻译或者网络传播等,侵权必究。
    4、如你看到网页展示的文档有www.zixin.com.cn水印,是因预览和防盗链等技术需要对页面进行转换压缩成图而已,我们并不对上传的文档进行任何编辑或修改,文档下载后都不会有水印标识(原文档上传前个别存留的除外),下载后原文更清晰;试题试卷类文档,如果标题没有明确说明有答案则都视为没有答案,请知晓;PPT和DOC文档可被视为“模板”,允许上传人保留章节、目录结构的情况下删减部份的内容;PDF文档不管是原文档转换或图片扫描而得,本站不作要求视为允许,下载前可先查看【教您几个在下载文档中可以更好的避免被坑】。
    5、本文档所展示的图片、画像、字体、音乐的版权可能需版权方额外授权,请谨慎使用;网站提供的党政主题相关内容(国旗、国徽、党徽--等)目的在于配合国家政策宣传,仅限个人学习分享使用,禁止用于任何广告和商用目的。
    6、文档遇到问题,请及时联系平台进行协调解决,联系【微信客服】、【QQ客服】,若有其他问题请点击或扫码反馈【服务填表】;文档侵犯商业秘密、侵犯著作权、侵犯人身权等,请点击“【版权申诉】”,意见反馈和侵权处理邮箱:1219186828@qq.com;也可以拔打客服电话:0574-28810668;投诉电话:18658249818。

    开通VIP折扣优惠下载文档

    自信AI创作助手
    关于本文
    本文标题:工程变更英文资料.doc
    链接地址:https://www.zixin.com.cn/doc/1801787.html
    页脚通栏广告

    Copyright ©2010-2026   All Rights Reserved  宁波自信网络信息技术有限公司 版权所有   |  客服电话:0574-28810668    微信客服:咨信网客服    投诉电话:18658249818   

    违法和不良信息举报邮箱:help@zixin.com.cn    文档合作和网站合作邮箱:fuwu@zixin.com.cn    意见反馈和侵权处理邮箱:1219186828@qq.com   | 证照中心

    12321jubao.png12321网络举报中心 电话:010-12321  jubao.png中国互联网举报中心 电话:12377   gongan.png浙公网安备33021202000488号  icp.png浙ICP备2021020529号-1 浙B2-20240490   


    关注我们 :微信公众号  抖音  微博  LOFTER               

    自信网络  |  ZixinNetwork