1、-精品word文档 值得下载 值得拥有-ering目 录Contents一、编制说明Explanation to the Compilation2二、工程概况 Project Profile2三、施工准备 Preparations for the Commencement3四、项目组织管理机构The Project Administration Organization6五、土建部分主要施工方法The Main Construction Method for the Civil Work8七、安装部分主要施工方法Main working plan for installation25八、季节性
2、施工措施Working plan for seasonality35九、质量保证措施Quality guarantee measurement39十、工期保证措施The steps for time limitation guarantee43十一、安全生产措施Security Production Measurement47十二、现场文明施工措施Field civilization working measures57十三、环境卫生保护措施Sanitation protectin measures58十四、施工总平面布置图The layout of the jobsite60十五、附图附表
3、The figure and attached list63一、编制说明Explanation to the Compilation1.1编制原则The Principles of the Compilation本施工组织设计只是根据业主所提供的资料以及结合现场条件、工程特点进行编制的,着重于施工方案、技术措施、施工管理措施、施工形象进度计划、现场平面布置、机械设备及人员组织机构配置、施工中的重点难点技术措施的编制。The present proposal, with a view to the bidding stage, is made and based on the technical
4、 specifications stated in the tender documents. It is concentrated in the execution plan, technical and management measures, progress scheme, site layout, machines and equipments, labor forces, site management organization and measures to be taken for the main and difficult work execution. It is onl
5、y a proposal made to comply with the project drawings and the details stated in the bidding documents. This company will compile one complete and detailed execution schedule based on the Project characteristics and design demands1.2编制依据Gist for the Compilation本工程根据乌干达国家标准局项目招标文件、设计图纸、结合现场条件及工程特点进行编制
6、;The compilation in accordance with bidding instruction, design drawing, site condition and the characteristic of project for Ungada National Bureau Of Standards Administration Block Project.二、工程概况 Project Profile本工程为新建工程,工程位于:乌干达坎培拉市区。总使用面积为4826 m,新建建筑占地面积约1000 m。新建建筑地下室一层,地上最高五层,建筑高度为22.4米。由乌干达政府投
7、资兴建,由Arch Forum Ltd公司设计。总工期为307天。This project is new construction, The site Located at Plot 2-12 by pass link, Bweyogerere.Total usable floor area is 4826 m, new construction occupies approximately 1000 m. The block is divided sub structure and super structure. The height is 22.4 meters. The client
8、is Uganda National Bureau of Standards. The lead consultant is Arch Forum Limited. The construction period is 307 days.三、施工准备 Preparations for the Commencement3.1现场准备 Site Preparation3.1.1按施工现场平面布置图搭建生产和生活临时设施,做好现场临时施工道路、施工用水电的布置、现场污水、雨水排放明沟,现场安全防护设施搭建等工作。Set up the temporary facilities for site pro
9、duction and life as per the site layout. Prepare well the temporary access, water and power, sewage disposal, rain water discharge and the safety protection facilities and etc. for the commencement.3.1.2布置好现场的工程概况牌、安全生产标志牌、劳动纪律牌等“一图五牌”。Set up at the site the two charts and six boards: the project pl
10、ate, safe production marks, work disciplines board and etc.3.1.3组织施工人员进场,并做好各项教育工作。Organize the work force, move into the site and do well educational work and others.3.2施工技术准备Preparations for execution techniques施工技术准备的主要内容,可以归纳为以下四个方面:一是组织图纸会审;二是编制开工前的各项方案、措施;三是进行工程定位,开展施工测量;四是完成技术、检验机制的建立。其具体内容是:
11、The main thing in this regard are the following four parts: study and examine the drawings; work out the schedules for the commencement; start the project location and surveying work; establish the mechanism of the technique identification and quality inspection. The details are:3.2.1及时组织技术人员,预算员认真熟
12、悉施工图纸,参与图纸会审和技术交底; Timely organize the technicians and quantity surveyors to get familiar with all the drawings. They shall participate in the drawings studying and examining, and explain all the technical details.3.2.2编制施工图预算和月旬作业计划,提供材料的需要量计划; Work out the project budget and the schedules for mont
13、hly and 10-days site work, and also the materials supply plan.3.2.3商请建设单位组织移交、规划红线、座标、标高等;Consult with the Client to hand over the site, plot lines, bench marks and levels, etc.3.2.4组织专业技术人员进行模板和钢筋的翻样工作; Organize the professional technicians to work out shop drawings for all the moulding board and s
14、teel work.3.2.5做好各种进场材料的质量检验等准备工作。Do a good job in checking all those materials to be brought into the site and concrete mix preparations.3.2.6根据工程施工需要,结合外围电网的情况和市政供水管网的情况,进行施工用电用水设计。Work out the consumption schedule for the water and power needed for the project as per the requirements of the proje
15、ct execution and the status of electricity grid and city water supply.3.3主要机械设备、周转材料及劳动力资源配备Preparations of Major mechanical equipments, cycling materials and work forces根据本工程的施工规模及结构形式,为了顺利快速地完成本工程,交付给业主早日投产使用,拟投入的机械设备及劳动力详下表。As per the project scale and structural formation and in order to smoothl
16、y complete the execution so as to hand over to the client for the early operation, it is proposed to allocate of the following equipments and labor forces as the form listed below:主要施工机械和材料一览表Major Machines and Materials for the Project序号S.No名称Descriptions型号Model数量Qty单位Unit用电量/台(KW) Power Consumptio
17、n 进场安排Date to bring in1挖掘机Excavator1辆Unit2.82砼搅拌机Concrete MixerJZC5001台Unit5.53砂浆拌和机Mortar MixerUJ2001台Unit2.24龙门吊GantryCrane2台Unit5钢筋切断机Cutting M/CGQ-401台Unit36钢筋弯曲机Bending M/CGW-401台Unit37电焊机Welding M/CBX1-5005台Unit23.48输送泵 Transfer Pump HBT60-13-9051台Unit909圆盘锯 Disc SawMJ1062台Unit5.510插入式振捣器Vibra
18、torsHZ6X-5010台Unit1.511平板振动器Plate CompactorPZ-5011台Unit0.512镝灯Dysprosium lamp4盏Unit13水准仪 water levelS31台Unit14全站仪 Total StationJ21台Unit15柴油发电机diesel-driven generator12V135AD1台Unit3.4劳动力资源配备 Labor Forces劳动力安排一览表Labor Forces List序号S.No.工种名称Trade数量Number单位unit备注Remarks 1泥工Mason20人person按实际开工日期陆续进场 Ente
19、rthe siteas per the requirementson site2木工Carpenter25人person3钢筋工Rebar man20人person4架子工Scaffolder5人person5电工Electrician8人person6龙门吊司机GantryCrane Operator2人person7砼工Unskilled Labor10人person8管道工pipeliner6人person9电焊工electric welding6人person10油漆工 painter2人person11铆工riveter1人person四、项目组织管理机构The Project Ad
20、ministration Organization4.1 现场项目部机构的设置 The setting for site project department organization4.1.1、项目经理部组织机构框图 The frame for project department organization施工组织机构框图The block diagram for site organization 决策层项 目 经 理 部 财 务 审 计 部管 理 层后 勤 保 障 部经 营 计 划 部物 资 采 购 部质 量 安 全 部工 程 技 术 部安装队土 建 队作 业 层41.2 项目经理部职能
21、:项目经理部对项目施工中的各项工作进行指挥、调度、管理和协调。The project department function: each item work is commanded, controlled, managed and coordinated in the construction of the project.41.21 项目经理部的决策层:由项目经理、项目副经理、总工组成,对本工程行使计划、组织、协调、控制、监督和指挥调度职能。 The Project decision layer: be made up of project manager, vice-project ma
22、nager and general engineer. This layer function is make plan, organization, coordination, supervision and control, command.41.22 项目管理层:在项目经理的领导下,由各职能模块负责人组成,对工程质量、技术、安全、成本等进行全过程的具体管理和协调控制。 The Project management layer: be made up of department principal. This layer function is specific management an
23、d coordination control for quality, technology, safety, cost of the entire project process.41.23 项目作业层:由具有熟练操作技能和操作经验的工人组成,项目实施中明确施工目标、责任和义务。 The Project implementation layer: be made up of workers who have skilled operation and operation experience.五、土建部分主要施工方法The Main Construction Method for the C
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- 乌干达 国家 标准局 施工组织设计 合并
1、咨信平台为文档C2C交易模式,即用户上传的文档直接被用户下载,收益归上传人(含作者)所有;本站仅是提供信息存储空间和展示预览,仅对用户上传内容的表现方式做保护处理,对上载内容不做任何修改或编辑。所展示的作品文档包括内容和图片全部来源于网络用户和作者上传投稿,我们不确定上传用户享有完全著作权,根据《信息网络传播权保护条例》,如果侵犯了您的版权、权益或隐私,请联系我们,核实后会尽快下架及时删除,并可随时和客服了解处理情况,尊重保护知识产权我们共同努力。
2、文档的总页数、文档格式和文档大小以系统显示为准(内容中显示的页数不一定正确),网站客服只以系统显示的页数、文件格式、文档大小作为仲裁依据,平台无法对文档的真实性、完整性、权威性、准确性、专业性及其观点立场做任何保证或承诺,下载前须认真查看,确认无误后再购买,务必慎重购买;若有违法违纪将进行移交司法处理,若涉侵权平台将进行基本处罚并下架。
3、本站所有内容均由用户上传,付费前请自行鉴别,如您付费,意味着您已接受本站规则且自行承担风险,本站不进行额外附加服务,虚拟产品一经售出概不退款(未进行购买下载可退充值款),文档一经付费(服务费)、不意味着购买了该文档的版权,仅供个人/单位学习、研究之用,不得用于商业用途,未经授权,严禁复制、发行、汇编、翻译或者网络传播等,侵权必究。
4、如你看到网页展示的文档有www.zixin.com.cn水印,是因预览和防盗链等技术需要对页面进行转换压缩成图而已,我们并不对上传的文档进行任何编辑或修改,文档下载后都不会有水印标识(原文档上传前个别存留的除外),下载后原文更清晰;试题试卷类文档,如果标题没有明确说明有答案则都视为没有答案,请知晓;PPT和DOC文档可被视为“模板”,允许上传人保留章节、目录结构的情况下删减部份的内容;PDF文档不管是原文档转换或图片扫描而得,本站不作要求视为允许,下载前自行私信或留言给上传者【可****】。
5、本文档所展示的图片、画像、字体、音乐的版权可能需版权方额外授权,请谨慎使用;网站提供的党政主题相关内容(国旗、国徽、党徽--等)目的在于配合国家政策宣传,仅限个人学习分享使用,禁止用于任何广告和商用目的。
6、文档遇到问题,请及时私信或留言给本站上传会员【可****】,需本站解决可联系【 微信客服】、【 QQ客服】,若有其他问题请点击或扫码反馈【 服务填表】;文档侵犯商业秘密、侵犯著作权、侵犯人身权等,请点击“【 版权申诉】”(推荐),意见反馈和侵权处理邮箱:1219186828@qq.com;也可以拔打客服电话:4008-655-100;投诉/维权电话:4009-655-100。